Chapter 5 - Material Requirement Planning









If you want to find out more about material requirements planning, please click https://www.youtube.com/watch?v=ubfHDXwy3aI









ACTIVITY


1) Complete the MRP record. Lead time for the part is two weeks and the order quantity is 40. The lot size is  50. What action should be taken ?


Week
1
2
3
4
Gross Requirement
20
15
10
20
Schedule Receipts




Projected Available       40




Net Requirements




Planned Order Receipt




Planned Order Release






2)Complete the MRP record. Lead time for the part is one weeks. The lot size is  100. What action should be taken ?


Week
1
2
3
4
Gross Requirement
20
65
30
20
Schedule Receipts




Projected Available       40




Net Requirements




Planned Order Receipt




Planned Order Release






3)Complete the MRP record. The master production schedule calls for 200 As to be available in week 4.  Lead time for the part is one weeks. There are 20 Fs available. All other on hand balanceis 10.

Parents
A
B
C
Components
B(2)
C(2)
F(1)
D(2)
D(2)
E(1)


4)Calculate 500 Gs in week 6. All lead time 2 week. Except for T is 1 week.

Parents
G
T
0
Components
M(2)
O(3)
P(1)
M(2)
O(2)
T(2)
M(2)
T(1)